Flood routing in reservoirs using synthetic unit hydrograph: The case of Bung Takreng Reservoir in Yom Basin, Thailand |
Date of Acceptance |
17 January 2014 |
Journal |
Title of Journal |
Advanced Materials Research |
Standard |
SCOPUS |
Institute of Journal |
Advanced Materials Research |
ISBN/ISSN |
|
Volume |
|
Issue |
|
Month |
|
Year of Publication |
2014 |
Page |
818-822 |
Abstract |
The disastrous flood that inundated many areas of the Chao Phraya basin in 2011 caused
many detrimental effects on the country’s economy and society. It is vital for all concerned to better
plan and manage these effects in order to minimize future disasters areas. Flood reduction requires
water flow detention or deceleration of during the storm water season. The construction of water
detention ponds is one solution that should be taken into account. This study investigated the
reduction of water flow in Yom basin (a sub-basin of Chao Phraya basin) using the synthetic unit
hydrograph to synthesize deluge parameters. The objectives of this case study are to utilize natural
lowland areas upstream of Yom Basin, namely Bung Takreng, Bung Kheerang, and Bung Raman.
These three swamps are adjacent to one another, so one detention pond system could be
constructed. The relationship between volume (S) and height (H) of the detention pond system was
found to be S=18866224.8H1.15 based on the analysis of elevation data using Geographic
Information System (GIS). The estimated inflow to the detention pond at different return periods
was based on the synthetic unit hydrograph. The maximum flow rate was analyzed by flood routing
through a modeled reservoir system. The reservoir system was assigned a 3 m height dyke over the
spillways, dividing into 2 m for the peak drainage and 1 m freeboard. Flood routing was performed
at the return periods of 2, 5, 10, 25, 50, and 100 years. We obtained the following safe lengths of
spillway: 30, 70, 100, 140, 175, and 210 m, respectively. The detention pond system can detain
water for 4 hr and reduce the peak flow in Yom River to 81.83, 84.44, 77.26, 81.00, 90.81, and
89.81m3/sec or 9.37, 5.75, 4.08, 3.30, 3.15, and 2.71 percent, respectively. Findings of this study
can be applied in decision making regarding the construction size of the reservoirs. In addition, the
results can be applied in developing other areas into detention ponds. |
Keyword |
detention ponds, flood routing, unit hydrograph, Yom Basin |
Author |
|
Reviewing Status |
มีผู้ประเมินอิสระ |
Status |
ตีพิมพ์แล้ว |
Level of Publication |
นานาชาติ |
citation |
false |
Part of thesis |
true |
Attach file |
|
Citation |